The contractor for the new development off Cornets End Lane is installing foundations for the new buildings. The site of the development was a former inert landfill with poor quality existing ground of demolition brick and rubble to 8m in depth. This material is not suitable to carry the new buildings so their foundations must pass through this poor quality ground.

The contractor is installing 10m long concrete piles which are being driven into the ground by two large Piling rigs so that the duration of this activity is kept to a minimum. These works started on the 23rd November and will be completed on the 19th December. We have received apologies from the Contractor who is working quickly to complete this noisy part of the project.

Update from Tony Wheby, Director E: tony@earthworm.ltd.uk