NRS – Meriden Aggregates Bank Holiday work
Apr 12, 2020
At meriden aggregates we have had an issue just surfaced yesterday that one of the lagoons on site seems to be leaking (the small one of the two). Because of this we have started to pump out the water to try to seal the banks and install overflow pipes. The work unfortunately will run for the next week we believe.
Unfortunatley this means NRS will be working sunday and monday till 1400 hrs. Machines will be kept to a minimum of three and all reversing beacons will be removed the work will not start till 8.00 am and most of the time they will be below road level so as to keep noise to an absolute minimum.